Barnet Plot One was delivered and erected in 5 working days. All of the external walls and floors were erected in two days. It took another day to get the steel purlins in position for the roof. After this it took us two days to have all the roof rafters cut and in position.By the end of the fifth working day the whole roof structure was ready to be made watertight with the underlay and battens.